4specs Discussion Forum » Specifications Discussions » what is "intermediate review" submittal? « Previous Next »

Author Message
Richard Fost AIA, CSI, CCS, CCCA, SCIP
Senior Member
Username: richardfost

Post Number: 14
Registered: 12-2008
Posted on Friday, March 08, 2024 - 04:51 pm:   Edit PostDelete PostPrint Post

in MSpec 013300 "Submittal Procedures", under 'processing time', the section includes (and has included for years) "intermediate review" in addition to, and between, initial review and resubmittal review.
I have been looking for an explanation of what an "intermediate review" is and have come up empty-handed thus far.

Also, I was a project architect for 15 years and am unable to think of a time 'intermediate submittal' came up on a project or was something I requested from a contractor - unless we called it by another name in the office.

So I wanted to ask here to see if anyone has sources for information or readings to suggest.

Thanks.
Nathan Woods, RA, CSI, CCCA, LEED AP
Senior Member
Username: nwoods

Post Number: 928
Registered: 08-2005


Posted on Friday, March 08, 2024 - 05:36 pm:   Edit PostDelete PostPrint Post

Well, in the design-build world, I often get "progress submittals", such as for curtainwall and exterior metal stud design......
Richard Fost AIA, CSI, CCS, CCCA, SCIP
Senior Member
Username: richardfost

Post Number: 15
Registered: 12-2008
Posted on Wednesday, April 03, 2024 - 04:11 pm:   Edit PostDelete PostPrint Post

Thanks Nathan. Understand progress submittals during design/build.

What's strange to me is that there seems to be no definition of what an "intermediate review" is - or what it would be for - in a project's submittal process.

Add Your Message Here
Post:
Username: Posting Information:
This is a public posting area. Enter your username and password if you have an account. Otherwise, enter your full name as your username and leave the password blank. Your e-mail address is optional.
Password:
E-mail:
Options: Automatically activate URLs in message
Action:

Topics | Last Day | Last Week | Tree View | Search | Help/Instructions | Program Credits Administration