Robin E. Snyder Senior Member Username: robin
Post Number: 513 Registered: 08-2004
| Posted on Thursday, February 27, 2014 - 04:56 pm: | |
It's RFI week for me!!! If a rated door assembly is tested by WH (instead of UL), would WH still neet to test (and show compliance with) UL 10c (or is that test only performed by UL)? |
ken hercenberg Senior Member Username: khercenberg
Post Number: 717 Registered: 12-2006
| Posted on Thursday, February 27, 2014 - 05:19 pm: | |
As far as I know, Interetek (WH) tests to UL 10(c) and many other standards. Check out their directory at https://whdirectory.intertek.com/Pages/DLP_Search.aspx |
Mark Gilligan SE, Senior Member Username: mark_gilligan
Post Number: 645 Registered: 10-2007
| Posted on Friday, February 28, 2014 - 09:08 pm: | |
WH needs to test to the standard listed in the code. If the code required UL to perform the test we would have a monopoly. If the Owner wishes to only allow tests per UL and states so in the specification then there is no problem. |