Richard L Matteo, AIA, CSI, CCS Senior Member Username: rlmat
Post Number: 473 Registered: 10-2003
| Posted on Wednesday, January 04, 2012 - 05:13 pm: |    |
I'm in the process of specifying Fire Extinguisher Cabinets and Fire Hose Cabinets & Hose Racks. I know the extinguishers & cabinets go in Divsion 10, but do the hose racks and cabinets go in 10 or 21 given the new MasterFormat system? I'm inclined to keep them in Div. 10 - Any thoughts? |
Lynn Javoroski FCSI CCS LEEDŽ AP SCIP Affiliate Senior Member Username: lynn_javoroski
Post Number: 1359 Registered: 07-2002

| Posted on Wednesday, January 04, 2012 - 05:56 pm: |    |
I'd agree and keep them in Division 10. |
Richard L Matteo, AIA, CSI, CCS Senior Member Username: rlmat
Post Number: 474 Registered: 10-2003
| Posted on Wednesday, January 04, 2012 - 07:01 pm: |    |
Thanks Lynn. That's what I did. |
John Bunzick, CCS, CCCA, LEED AP Senior Member Username: bunzick
Post Number: 1352 Registered: 03-2002
| Posted on Thursday, January 05, 2012 - 09:16 am: |    |
Normally 10, but in my old office they were in 21 for coordination purposes - both in design and in construction. |
|