Jerome J. Lazar, RA, CCS, CSI, SCIP Senior Member Username: lazarcitec
Post Number: 152 Registered: 05-2003
| Posted on Thursday, September 08, 2005 - 01:40 pm: |    |
Have a project where we need to specify extensive demolition of existing horizontal structural elements on multiple levels, while retaining the existing vertical structure and foundations - would we be better off using section 01732- Selective Demolition or Section 02220 - Building Demolition? |
Dave Metzger Senior Member Username: davemetzger
Post Number: 132 Registered: 07-2001
| Posted on Thursday, September 08, 2005 - 01:47 pm: |    |
I'd use selective demolition; we just use the building demolition section for demo of entire building, not portions. Make sure that the contractor is responsible for temporary bracing and shoring to maintain the structural integrity of structure to remain. |
Lynn Javoroski Senior Member Username: lynn_javoroski
Post Number: 237 Registered: 07-2002
| Posted on Thursday, September 08, 2005 - 02:03 pm: |    |
I agree with Dave on using selective demolition. I've used it in a Division 2 Section, too, when elements of a building will be demolished completely prior to the start of construction. In your case, though, it seems like you will need to leave the shoring and bracing there for at least part of the construction. Putting it in Division 1 makes more sense in this case, as it will apply to and cover the entirety of the Work. |
William C. Pegues, FCSI, CCS Senior Member Username: wpegues
Post Number: 483 Registered: 10-2002
| Posted on Thursday, September 08, 2005 - 02:08 pm: |    |
Jerome, I second Dave's response - I reserve building demolition for complete demolition. |
G. Wade Bevier, CSI, CCS, LEED-AP Member Username: wbevier
Post Number: 3 Registered: 07-2004
| Posted on Thursday, September 08, 2005 - 02:23 pm: |    |
MasterFormat 2004 includes a section in the new Divison 02 Existing Conditions; 02 41 19 - Selective Structural Demolition Might not help if you are using the 95 version but I would modify the Selective Demolition section to suit the project. |