Author |
Message |
David Axt, AIA, CCS, CSI
Senior Member Username: David_axt
Post Number: 136 Registered: 03-2002
| Posted on Wednesday, June 18, 2003 - 06:21 pm: | |
A sub called today about a question on our chain link spec. I look at the files on my computer and realized I did not have the section. So I told him that Civil wrote the spec. The sub called back and said Civil said we wrote the spec. After fooling around, I realized that the Athletic Field Consultant wrote the spec. This made me think. Why not identify the author of the spec sections? We identify the author of the drawing sheets. Your comments please. |
Richard Hird (Unregistered Guest) Unregistered guest
| Posted on Wednesday, June 18, 2003 - 06:57 pm: | |
David: I do not believe any of the consultants should be named on the drawings let alone in the specifications. It helps keeep the information chain clean. All questions should go first to the Architect. He should know who made the decisions, and is the only one that should answer. It may be an overreaction, but it makes the point, the Consultant is not authorized to make changes. |
William C. Pegues, FCSI, CCS
Senior Member Username: Wpegues
Post Number: 170 Registered: 10-2002
| Posted on Thursday, June 19, 2003 - 12:09 am: | |
I absolutely agree with Richard. We, as the architect, create a drawing format for a particular project. It includes the names of the company information of the consultants. Everyone uses the same titleblock, there is no separate identification as to who has done what drawing, it reads like a single combined effort, just as the project manual does. And on the project manual, in our introductory information we have a 'fly sheet' that includes same information. Sometimes at an Owner will request that an independent consultant have their work issued with ours. Neither for drawings nor project manual elements do we bind it into our sets. As a courtesy we will coordinate the printing - I create a separate cover and booklet for project manual elements so it appears in its own separate bound book but it is not even referenced in ours. Same for the drawings, we will send them out to the printer and they will have a separate binding on these other drawings. Here in our area, Washington DC, civil, geotech, building security, and building signage are almost always separate consultants to the Owner whose documents are separate and not combined with our. Some of our Owners also deal with landscaping as a separate consultant not part of the project team. And if they have a separate architectural lighting consultant, they too are almost always totally separate from our documents. For high rise apartments and condos here, the owners will often take separate design services proposals for the main public spaces (lobbies, upper level lobbies and corridors, specialty rooms like party rooms, fitness centers, etc.) and though we also have a complete interiors department, they don't always get the contract for interiors, so those drawings and specification information are also totally separate packages. William |
DennisHall (Unregistered Guest)
Unregistered guest
| Posted on Thursday, June 19, 2003 - 07:44 am: | |
As with William, our firm creates one title block with all design professionals listed. However, as required by law in North Carolina, the indivisual designers must affix their seals to their work. Further, the sheet identification, (UDS/NCS for sheet number) identifies the discipline by a single character, A for Architectural, S for Structural, etc. We also include on Document 00001-Project Title Page, the list of all project design professionals, including names, addresses, telephone, fax, and e-mail addresses. We go further list on Document 00005- Certifications Page of the project manual all sections of the Specifications (Division 1-16) under the name and signature of the responsible design professional which claims aurthorship of the work. This keeps the chain of responsibility clear. In cases where we are only acting as the specification consultant for an A/E firm, we are listed as such on the Project Title Page, however, the Architect of Record is listed as the author of the appropriate specifications on the Certification Page. We have been doing this for years and have had no problems. |
Marshall Fryer (Unregistered Guest)
Unregistered guest
| Posted on Thursday, June 19, 2003 - 08:31 am: | |
Richard Hird stated, and I concur, that "All questions should go first to the Architect." Should it also be stated that all questions from subcontractors should go first to the general or prime contractor? |
John Bunzick, CCS, CCCA
Senior Member Username: Bunzick
Post Number: 108 Registered: 03-2002
| Posted on Thursday, June 19, 2003 - 10:03 am: | |
I do believe that the 'authors' of the various parts of the contract documents should be identified. I have occasionally seen specs identified by the major consultants - after all, they are usually identified on the drawings. I see nothing wrong with this, and in fact, as Dennis points out, there are legal issues, at least with the licensed professionals. Plus, I think that the consultants deserve recognition for their work. There's no go reason to keep their identity bottled up and hidden. Hopefully, the project architect knows off the top of her or his head who wrote each spec section! On the other hand, communications should go through the GC to the Architect to the consultant. This is true in part because those subs and consultants work for the GC and the Architect, and also because those two firms serve as the "integrators" of information - every decision affects something else. I usually advise both the GC, the subs and my consultants at the start of the job that I don't want them talking directly except under specific circumstances. Often during construction, having direct conversations (such as between the steel fabricator and the structural engineer) is necessary due to the "language" spoken. If I have a good consultant, they advise me in writing of every conversation for the record. |
Anne Whitacre, CCS CSI
Senior Member Username: Awhitacre
Post Number: 64 Registered: 07-2002
| Posted on Thursday, June 19, 2003 - 01:51 pm: | |
I agree with the last couple of posts: in the table of contents, I typically identify the preparing party for the spec sections, and our drawings are identified by preparer, also. We used to separately issue those documents prepared by the consultants to the Owner (geotech, etc) but now these are bound into our documents with a notation either on a section cover sheet or on the table of contents as to who the preparer (ie, responsible party) is for that portion of the documents. I've found that this cuts down on questions to us in some cases; provides a clear an easy method of identifying the responsible firm for document preparation; and also serves as a check for me when I get questions 1 year and 30 jobs later... As for project questions: I agree entirely with Mr. Bunzick's second paragraph. |
David Axt, AIA, CCS, CSI
Senior Member Username: David_axt
Post Number: 137 Registered: 03-2002
| Posted on Thursday, June 19, 2003 - 03:00 pm: | |
If the chain link section had not had the words "copyright 2003 XXXXX Consultant". I would have never figured out who wrote the spec. The project has stopped and started for 3 years and the project architect is on vacation. Sometimes the project managers have me put a Project Directory in our specs that list all the consultants. Our drawing titleblock has a list of all the consultants and address and phone #'s. Engineers and Architects are required to put a stamp on the drawing sheets that they prepared. Although I agree that all questions should be directed through the architect, we should not try and conceal the information of who prepared what. I always wondered why our table of contents has a letter after the section number identifying the consultant, i.e. Section 02230 C - Site Clearing. "C" stands for Civil Engineer.
|
William C. Pegues, FCSI, CCS
Senior Member Username: Wpegues
Post Number: 173 Registered: 10-2002
| Posted on Friday, June 20, 2003 - 06:17 pm: | |
I would agree that if you are including sections that are not part of the architectural team (architect and consultants to the architect) that not only is it a good idea to indicate which sections are by consultants to the owner - but that its really necessary. You need to identify that work for which the architect is not responsible - most particularly, not responsible in maintaining the current status of the document. You have no real way of knowing if they ever revise them or reissue them or even replace them...and that's for both drawings and specifications. Which it the reason that we don't put them in the project manual - and that's still the best position. William |
John Regener, AIA, CCS, CCCA, CSI, SCIP Senior Member Username: John_regener
Post Number: 90 Registered: 04-2002
| Posted on Friday, June 20, 2003 - 06:34 pm: | |
Who would be the author of Section 03300 - Cast-in-Place Concrete? Is it the structural engineer or the architect? or the civil engineer whose drainage structures use cast-in-place concrete? of the landscape architect whose gazebo has concrete footings? or the mechanical engineer whose boiler has a raised housekeeping pad? or the electrical engineer whose transformer has a slab on grade and whose parking lot pole-mounted area lights have concrete foundations? Sometimes there are multiple responsibilities. As I understand the Project Manual concept ... and I guess I have a rather liberal viewpoint ... anything that can fit between the covers of the Project Manual can be in the Project Manual, whether it is part of the MasterFormat numbering or not (I'm thinking of "Appendices" which can contain all sorts of referenced documents). For two recent projects, the signage consultant produced an elaborate document that contained both drawings and specifications but the specifications did not conform to SectionFormat and PageFormat. Rather than go through a dispute, I included the signage document in the Project Manual as an Appendix. I won't win a CSI specifications competition but it worked fine for both bidding and construction. |
Richard Hird (Unregistered Guest) Unregistered guest
| Posted on Saturday, June 21, 2003 - 10:25 am: | |
David As specification writer I try hard to meet the needs of designers that do not show what needs to be shown on the drawings bidders that do not define trade scopes during bidding contractors that do not hire qualified subcontractors and tradesman lawyers that can not make a case solely on what is right and wrong insurance companies that do not intend to cover what goes wrong Even though I should not have to be concerned about any of the above I do. Hopefully you will forgive me for “not caring” about a management that can not find their files. |
David Axt, AIA, CCS, CSI
Senior Member Username: David_axt
Post Number: 138 Registered: 03-2002
| Posted on Monday, June 23, 2003 - 12:14 pm: | |
John, Typically the architect is the author of Section 03300 - Concrete, with input from the Civil/Structural Engineer. I am talking about sections that we get from our consultants that we just stick into the project manual. I believe that these consultant prepared sections need to be identified if only by a code. This would also help our CA people track down who they should ask questions. David |
DennisHall (Unregistered Guest)
Unregistered guest
| Posted on Wednesday, June 25, 2003 - 07:50 am: | |
Just for the fun of discussion, there was a proposal that MasterFormat Section numbers should begin with a Discipline Designator similar to the NCS for drawings. This would mean you could have structural concrete, architectural concrete, mechanical concrete, electrical concrete, etc. They might look like this S-03300, A-03300, etc. The project manual would be organized by disciplines again similar to drawings. The task team would not support the idea and so we had other suggestions to consider. The reason for identification of the author of the Section has nothing to do with the lines of communication, and everything to do with responsibility for content. We currently have a project and the structural engineer is responsible for 03300- Cast-in-place Concrete inside a turbine building of a nuclear station. We are happy to allow them have the responsibility for this work, besides they work directly for the Owner not the Architect (me). We also have design work which the Owner is responsible for. Now, do you think I am happy to allow them to be responsible for this work? Heck yea! And we eagerly attach their name besides the Project Manual Sections which they prepared. PS. John, there is nothing wrong with an Appendix in a Project Manual. I don't usually have them, but it is an acceptable way of handling stuff that needs to be shared with the bidders and contractors.
|
Ralph Liebing
Senior Member Username: Rliebing
Post Number: 20 Registered: 02-2003
| Posted on Wednesday, June 25, 2003 - 09:37 am: | |
IF [????] we see a need to ID the author [and many of us do not!] let's keep it simple [I agree that the Task Force should reject the prefix letter]-- so how about this, IF necessary? SECTION 00000 - XXXXXXXXXX [centered] Prepared By: _________________ Checked By: __________________ PART 1 – GENERAL 1.1 SUMMARY etc. |
Margaret G. Chewning CSI CCS
Junior Member Username: Presbspec
Post Number: 5 Registered: 01-2003
| Posted on Wednesday, June 25, 2003 - 11:03 am: | |
In this age of electronic media, even for wordprocessing, and I am not aware of anyone who produces a spec without it. How about using the Hidden text feature or a comments note that can be inserted into the electronic copy for the record to identify the "Prepared by and Checked by" information. I feel putting it into the printed text adds clutter that is not needed to build the project. |
David R. Combs (Unregistered Guest) Unregistered guest
| Posted on Wednesday, June 25, 2003 - 03:16 pm: | |
The hidden text is a good idea, and I agree with my NoVA colleague regarding the added "clutter," but I think I need to side with Dennis on this one. The Document 00005 - Certification Page seems to be the best place, not only for authorship but for professional seals as well. I've run across too many issues and scenarios that only the Certification Page would solve, such as: 1. A structural engineer prepares their Division 6 sections (for a large wood-frame building) so poorly that they basically have to be re-written, supplemented, and re-formatted, not to mention actually edited for the project (thank goodness I had their electronic copy). I ended up spending unnecessary (and non-budgeted) hours cleaning up their mess. Ultimately, I ended up being the author, not the structural engineer. 2. The CA department does not have computer rights or access to the specifications folder, or if they do, they don't have the know-how to be able to turn on the hidden text. 3. The consultants don't give us electronic copies of their sections, only hard copies. Hence, no ability to view the hidden text. 4. Specifications prepared by consultants not in sequence, i.e. structural (earthwork for building pad and drilled piers - Div. 2, concrete - Div. 3, structural steel - Div. 5), M/E/P (fire alarm and fire protection - Div. 13 [when you can get them to do ther instead of in 15 and 16!], mechanical - Div. 15, electrical - Div. 16) are just some examples. There's also the civil and landscape stuff intermixed with the rest of Div. 2, which is sandwiched between Div. 1 (by architect) and Div. 3 (some by architect, some by structural). And then there's the sound/acoustical consultant writing their own Div. 16 sections - which the elctrical engineer won't seal. The professional seals - which end up being scattered all over the T of C pages, may be in the vicinity of the specifications prepared by that consultant, but are not specifically identified as being associated with, or having been prepared by, that particular consultant. 5. Proper identification of specifications prepared by Owner's outside consultants, without them appearing on the same page, or adjacent to, specifications prepared by other consultants. Seems like the Certification Page would fix all that. Plus, with the information readily available to the end-users of the Project Manual, the subcontractor would not have called the architect directly in the first place. He would have called the consultant. Still wrong (should go through the GC), AND the CA person was left out of the loop! Hmmmm . . . now THERE'S a case for keeping them guessing. It's so nice the feel needed. :-) |
Robert Swan (Unregistered Guest) Unregistered guest
| Posted on Tuesday, July 01, 2003 - 05:56 pm: | |
This discussion started because a sub wnated to talk directly with someonw other than the Architect - in other words violate the proper communications chain. The Architect of Record can keep any kind of sheet in his office to know where the author of any and all sections of the manual can be located, but please why contribute to your own troubles by publishing the author's name. You want to be aware of and control the information on your own project. The Certifications Section is the proper location for identification of the author of each section, so how did the Architect issue a manual without knowing another party wrote the section? |
William C. Pegues, FCSI, CCS
Senior Member Username: Wpegues
Post Number: 177 Registered: 10-2002
| Posted on Wednesday, July 02, 2003 - 05:49 pm: | |
Robert, I absolutely agree. Its really easy to track on a duplicate table of contents who did what. It invites direct and uncontroled contacts to the consultant author of specific sections - and that invites someone to give an uncoordinated answer and potential problems. There is simply no need, and no real rational, that can stand up to logic as to why someone would do this on individual sections. The only exception is that one situation where you are forced or required to publish in the project manual documents by others not in the design team, direct consultants to the owner. William |
Margaret G. Chewning CSI CCS
Member Username: Presbspec
Post Number: 6 Registered: 01-2003
| Posted on Wednesday, July 02, 2003 - 07:37 pm: | |
The above brings me back to the use of hidden text and comment fields within the document. The information is there and is visible to those that need to get to it, (the designer/specifier) without cluttering the information needed to build the job. It's easy to do, track, and doesn't get lost from the original document. |
John Bunzick, CCS, CCCA
Senior Member Username: Bunzick
Post Number: 112 Registered: 03-2002
| Posted on Thursday, July 03, 2003 - 08:32 am: | |
As to the argument that putting the author of the specification section in the project manual invites direct contact: You would have to keep their identity secret throughout the entire construction phase for that to work. As soon as one memo or other bit of information is mentioned as to who the "kitchen consultant", "structural engineer", etc. (make your own list) is, the problem instantly returns. I'd rather make sure my consultans know the proper protocol along with the contractor and the subs, and emphasize procedure from the start of construction. There's another dirty secret to this issue. Most architects do not have sufficient fee (often because the owner doesn't see the value - ah, but I'm getting off track again) to provide much staff during CA. Thus, as an example, I have been the single person on a $50 million project. If every conversation goes through that one person, they become rather a bottleneck. As long as the documentation is appropriate, selective direct contact can serve a useful purpose. Sometimes pragmatism has to win out over the correct methods. If you've been there, you know what I mean. |
Curt Norton, CSI, CCS
Advanced Member Username: Curtn
Post Number: 18 Registered: 06-2002
| Posted on Thursday, July 03, 2003 - 09:37 am: | |
John, excellent point! We have a strong emphasis on CA at our firm, but neither the CA nor the PM/PA is going to be able to talk to the steel fabricator, the lab contractor and the mechanical contractor intelligently about every topic. We make sure consutants and all contractors understand that questions go through us, in writing, and when everyone starts following the rules, then we let them start to have direct conversations as needed, with a clear understanding that the CA is copied on all decisions. As for the project manual, it doesn't matter whether you identify the author or not. (I doubt most PA/PM's could tell you who wrote which sections of a spec, so I would think they would just ask their spec writer!) It's all about taking control of the project from the begining, regardless of fee. (Doesn't it cost more to try fixing those problems down the road?) |
dhall@hallarch.com (Unregistered Guest)
Unregistered guest
| Posted on Thursday, July 03, 2003 - 05:45 pm: | |
Each project is unique with it's own special requirements. The specifier and the Project Manager should first determine if the consultants need to be identified for the project. This decision may depend on many factors including whether you have a strong person handling the CA. My initial point was, if you chose to identify the consultants, and that is our firms general policy, here is the method we have found that works well. This is not unlike the decision to use broad or narrow scope with sections in your project manual. There is no right or wrong approach, but there may be poor execution of both approaches. The decision as to identification of consultants may be a personal one, how you do it is a professional decision. |
William C. Pegues, FCSI, CCS
Senior Member Username: Wpegues
Post Number: 178 Registered: 10-2002
| Posted on Sunday, July 06, 2003 - 09:28 pm: | |
We identify who a consultant is, even have their phone numbers - what we don't do is identify on a per section basis. The point is not to keep the communication line secret - no one has suggested that, that would be a joke. But direct communications should only take place after the correct process for doing so is put in place. There is no good reason why you need to identify the author - other than for internal purposes. And then there are many ways to do that without turning the section numbers and titles into a joke in the table of contents. William |
Phil Kabza
Intermediate Member Username: Phil_kabza
Post Number: 7 Registered: 12-2002
| Posted on Thursday, July 17, 2003 - 03:12 pm: | |
In addition to our firm name, we also place the names of those consultants required by statute to seal their documents in the footers of the sections they have prepared - we find this more useful than detailing their scope on the Seals Page, which could become separated from the document at a later date. This solution appears to meet requirements of the state licensing boards and the interests of the authorities having jurisdiction. It gives permanent publication record of the design professional firm responsible for the preparation of the document. Unlicensed consultants, such as food service equipment consultants, are not cited. We purge all our specifications sections of hidden text or tracked changes prior to publication and archiving. We'll be happy to be deposed concerning what we included in our specifications, but are less interested in having to comment on what we took out. |
Dennis Hall (Unregistered Guest)
Unregistered guest
| Posted on Sunday, July 20, 2003 - 12:54 pm: | |
We are seeing more and more specification sections being prepared by non-lisenced firms and indivisuals. I was speaking to a consultant this week that told me that the local county Park and Rec. Department prepares the playground equipment section and gives it to them for inclusion in the project mannual. The Owner or their attorney many times prepares the Series 0 documents. Giving credit and identifying responsibility for the preparation of written construction documents is not only a good practice it is important to share design liability with the parties that generated the information. Why should this consultant be responsibile for work proformed by the Owner. I firmly believe that everyone who does work on a project should be responsible for that work. Why should the Architect be resopnsible for the food service kitchen designer's work? This is particularly true when the Owner may have hired the consultant. We are just assembling a set of documents prepared by many players to show the complete work. Coordination is a different story and this is not intended to relieve the Architect from their responsibilities identified in their agreement, but these can vary greatly. Let's identify all participants who parpared written and graphic construction documents and make it clear that they are going to be held accountable for responsible work. |
Robert E. Woodburn, CCS, CSI Intermediate Member Username: Bob_woodburn
Post Number: 5 Registered: 05-2003
| Posted on Monday, July 21, 2003 - 01:49 pm: | |
"...identifying responsibility for the preparation of written construction documents is not only a good practice it is important to share design liability with the parties that generated the information. Why should this consultant be responsibile for work proformed by the Owner..." Identifying authors involves a potential liability pitfall. I don't know about other states, but here in Texas, "An Architect shall seal, sign, and date any document issued for regulatory approval, permit, or construction which was prepared by a consultant [my comment: licensed or otherwise, apparently] retained by the Architect who did not affix a professional seal to the document. An Architect is not required to seal documents that have been sealed by other licensed professionals." (This is a recent revision. Before 8/2/2002, I believe, the Architect's seal was required, in addition to those of the other professionals, on all documents.) If an architect includes spec sections, hardware schedules, etc. that have been prepared by unlicensed professionals (that have not been "retained by the Architect") in the project manual, should they be included as "Appendices" or "Information Available to Bidders" with the Architect's specific disclaimer of responsibility, and bound in and listed in a way that explicitly excludes them from the content being sealed and signed? Obviously, the Owner's own front-end documents can't be relegated to an appendix. Typically they aren't prepared by an Architect-retained consultant or sealed by the Owner's licensed professional. Is the Architect responsible for them, if they are not in some way excluded from the content that is sealed & signed? How would one do that? And what would the Owner think? It appears that other authors or sources perhaps should be identified where the purpose is to specifically exclude them from the responsibility of the design professional of record. However, if consultants that are "retained by the Architect" do not seal their own work, then it appears that the resulting documents are the Architect's responsibility, whether he or she wants them to be: They must be sealed and signed. Since unlicensed preparers can't seal them, the Architect must, thus bearing responsibility for all unlicensed consultants "retained". In that case, identifying the author to shift responsibility would seem futile. In a hostile environment (e.g., in court), could it even be construed as an attempt to dodge responsibility? IMO, attributing documents to their authors, if done at all, ought to be done very carefully. I don't recall ever encountering a firm with a well-developed policy (or any policy) in that regard; I would think that, for now, it lies outside of the "standard of care". Perhaps authors should be identified, or not, only when useful to reflect actual responsibility for particular documents -- clarifying, explicitly, who is liable for what, and who is not.
|
Phil Kabza
Advanced Member Username: Phil_kabza
Post Number: 8 Registered: 12-2002
| Posted on Wednesday, July 23, 2003 - 06:21 am: | |
I think Bob's point regarding owner-prepared front end documents is particularly well taken. We frequently encounter these documents. Many are fine, but some are poorly drafted and counter to accepted construction industry practice and case law. We don't touch these owner documents, other than to add the owner's name in the footer. Many questions surrounding unlicensed consultants preparing specification sections are yet to be answered. North Carolina public bidding laws forbid architects to publish drawings and specifications prepared by vendors with an interest in bidding on the public projects - a fact that is often a surprise to those parties engaged in just this sort of thing. There's been a "seal it now, ask questions later" kind of approach to incorporating work of other parties in our documents. I'd sure like someone from the professional liability insurance side of things to jump in here. |
dhall@hallarch.com (Unregistered Guest)
Unregistered guest
| Posted on Wednesday, July 23, 2003 - 07:56 am: | |
I had a meeting yesterday with the local county government and their CM for a major project, which we are the specifications consultant. The 0 Series documents were prepared by the CM and the Owner. They contain many Division 1 subjects. I made it perfectly clear that my client, the Architect, did not prepare these documents and would not place his seal on them. I further indicated that I expected the author of those documents to be prepared to defend them in court if necessary. The final result of that meeting is the Project Manual is being prepared in two volumes. Volume 1 is prepared by the Owner and CM and Volume 2 by the A/E and their consultants. The A/E will seal their work in Volume 2 and the Owner is responsible for the contents of Volume 1. We of course had some coordination to do to remove all items covered in Volume 1 from Volume 2, but we were happy to let others assume this responsibility. Everyone left the meeting feeling they had won. Footnote: The tought part of the meeting was when they pulled out the project manual for a sister project and it had been sealed by two architects (violation of NC Board of Arch. Regs.) and most of the Division 1 titles used by the A/E were basterized and did not match MasterFormat. The question from the CM was, why can't you just do that and use the same titles and numbers as this other guy? After explaining that the MasterFormat Police would probable not come to arrest us, but it offended our sence of logic to do it wrong. They finally came to the conclusion that were crazy and understood that agreeing with us would be easier than aruging with the insane. At this point the Owener had already left the meeting, as owners (particular government agencies) have not problem in dealing with insanity but the CM is mostly concern with money and they saw no monetary gain in the debate. The irony of this is that the firm that prepared this project manual with all the basterized section titles is a large A/E firm and their director of specifications from the mid-west is one of the folks that sent me long emails about proper specificationing in regard to development of MF 04. |
Robert E. Woodburn, CCS, CSI Advanced Member Username: Bob_woodburn
Post Number: 6 Registered: 05-2003
| Posted on Friday, August 01, 2003 - 10:16 am: | |
When two or more licensed professionals are involved together in the preparation of a particular specification section -- for example, 03300, jointly edited by the architect, and the architect's structural (and/or civil) engineering consultant(s) -- should all be identified as jointly responsible in the Project Manual, and affix their respective seals to that section? If so, how should they be identified? Or should only one? If so, who, and why?
|
Phil Kabza
Senior Member Username: Phil_kabza
Post Number: 12 Registered: 12-2002
| Posted on Wednesday, August 06, 2003 - 11:36 am: | |
Robert, I would think that the the professional whose editing had the most effect on the public's health, safety, and welfare should be the one to have final control over items affecting those issues and seal the section. As an architect, I am interested in the quality of the concrete finishes. The structural engineer determines how the concrete holds the building up. He wins. His seal. |
C. R. Mudgeon
Intermediate Member Username: C_r_mudgeon
Post Number: 7 Registered: 08-2002
| Posted on Wednesday, August 27, 2003 - 12:12 am: | |
Assume for a moment that an architect is the design professional responsible for a project, and that structural, mechanical, electrical, and other consultants work for that architect. Question: Who is responsible for the project? Answer: The architect. All of the engineers, though required to be registered, work for the architect. And when the excrement hits the impeller, it is the architect who is responsible. The structural design was incorrect? The architect has to answer first, then go after the structural engineer for non-performance. The same goes for other consultants. So who cares who the other consultants are? Why shouldn't the project manual and drawings be signed only by the architect? |
John Bunzick, CCS, CCCA
Senior Member Username: Bunzick
Post Number: 126 Registered: 03-2002
| Posted on Wednesday, August 27, 2003 - 08:45 am: | |
That is true for contractual issues, and relations with the owner. However, the reason we have licensing is because there is an overarching public policy issue. If there is a structural collapse, for example, the government can and will go directly to the structural engineer of record regardless of her or his contractual relationship with the architect. Although they may go after the architect too, its the engineer who's in deep trouble. |
Robert E. Woodburn, RA, CCS, CCCA,CSI Senior Member Username: Bob_woodburn
Post Number: 11 Registered: 05-2003
| Posted on Wednesday, August 27, 2003 - 04:19 pm: | |
"C. R. Mudgeon" writes, "Assume for a moment that an architect is the design professional responsible for a project, and that...other consultants work for that architect. Question: Who is responsible for the project?...Answer: The architect." Not necessarily. Responsibility is not simply determined by who works for whom. That's why drawings are signed and sealed -- to indicate responsibility, explicitly. As mentioned above in my July 21 post, Texas used to require the architect's seal on their engineering consultants' drawings, in addition to the engineers'. That policy, which tended to impute more responsibility to the Architect than was deserved, has been changed; architects no longer have to seal documents sealed by their licensed consultants. Each bears the primary responsibility for matters pertaining to his or her own discipline and expertise, as John Bunzick just pointed out. That, C.R., is the essence of what professionalism - and licensing laws - are all about... |
|