Brett M. Wilbur CSI, CCS, AIA Senior Member Username: brett
Post Number: 187 Registered: 12-2004
| Posted on Tuesday, November 17, 2009 - 05:17 pm: | |
It sems LEED and other sustainability sections were not included in MF04. Anyone have an idea where they fit in? Both Arcom and BSD ahve added them but they are not the same and honestly, they don't make sense. Sustainable Design Requirements is in 018113 but LEED credit reporting is like 013329. Cart before the horse. Where can I find an "official" MF04 list of these required sections? Or do I make it up myself? |
Wayne Yancey Senior Member Username: wayne_yancey
Post Number: 288 Registered: 01-2008
| Posted on Tuesday, November 17, 2009 - 05:24 pm: | |
Brett, Our section # - names are: 013544 - CONSTRUCTION INDOOR AIR QUALITY MANAGEMENT 013545 - SAMPLE IAQ PLAN 013456 - LEED CERTIFICATION PROCEDURES 013547 - CARPET RECLAMATION 017421 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017423 - FINAL CLEANING 019700 - COMMISSIONING |
Gary L. Beimers, FCSI, CDT, CSC Senior Member Username: gbeimers
Post Number: 26 Registered: 05-2005
| Posted on Tuesday, November 17, 2009 - 11:30 pm: | |
Brett, 013329 and 018113 were/are existing MF04 sections Also - 017853 Sustainable Design Closeout Documentation The MasterFormat Maintenance Task Team has added the following: 01 33 29.01 Material Cost Summary Form 01 33 29.02 Wood-Containing Product List 01 33 29.03 Metal-Containing Product List 01 33 29.04 Material Content Form 01 33 29.05 New Product Source Form 01 33 29.06 Reused Product Form 01 33 29.07 Prohibited Content Installer Certification and 01 35 46 Indoor Air Quality Procedures 01 35 63 Sustainability Certification Project Requirements 01 35 66 Sustainability Certification Project Procedures |
John Bunzick, CCS, CCCA, LEED AP Senior Member Username: bunzick
Post Number: 1136 Registered: 03-2002
| Posted on Wednesday, November 18, 2009 - 08:29 am: | |
We use: 01 81 13 Sustainable Design Requirements: This section will have the same title and number regardless of the certification method we are using for the project (one of the LEEDs or CHPS). We have multiple versions, but only one is ever used on a project. We have a "Sustainable Materials Attributes Submittal Form" which is attached to the Sustainable Design section. 01 57 33 Temporary Indoor Air Quality Control: This is of our own creation. They are temporary, so that's why I paired it with the temporary facilities area. As to the "cart before the horse," I'd urge that we don't think of Division 01 happening in chronological order. While there is a bit of that in its organization, it is really set up in groupings of types of activities. |
Brett M. Wilbur CSI, CCS, AIA Senior Member Username: brett
Post Number: 188 Registered: 12-2004
| Posted on Wednesday, November 18, 2009 - 09:53 am: | |
John, I agree with you about the chronological order. I'm just looking for something that makes sense to me and how I believe contractors think. i've rearranged some tof the numbers myself. I've put the credit summary report in the Summary activities group but this still doesn't make sense to me. That is really what I meant by cart before the horse. Describing the crdit requirments before you've even introduced them to the sustaniblity procedures or requirements which occur in 018113 in performance activities. Weird, but I will work it out. I like what the task team has done. It is very similar to what Speclink has done. Thank you everyone for your input. Hope some more people will chime in too. It's an interesting topic that goes to the heart of specification logistics and organization. |