Asbestos Survey Report prepared by a consultant on an existing building that is to be renovated. What is proper location in Project Manual, 00 31 26 Existing Hazardous Material Information or 02 26 23 Asbestos Assessment? |
Ronald L. Geren, AIA, CSI, CCS, CCCA, SCIP Senior Member Username: specman
Post Number: 556 Registered: 03-2003
| Posted on Tuesday, October 23, 2007 - 10:04 am: | |
00 31 26 is the correct location. This is information that is available to the bidders. Section 02 26 23 is used when you want the contractor to perform an asbestos assessment. |
Ron Beard CCS Senior Member Username: rm_beard_ccs
Post Number: 231 Registered: 10-2002
| Posted on Tuesday, October 23, 2007 - 02:38 pm: | |
Ronald is correct. ID the documentation as information prepared for use by the design team and clearly specify that the document is available to bidders "For Information Only," similar to what should be done with geotech; lead, mold,or other hazardous reporting; and other on-site surveys. |
|